How aggravating is it to watch this project held up by work on that little bridge just north of Still River Road? That's a rhetorical question. Commuters and non-commuters alike are "angry as hell" and "don't want to put up with it any more." (Network was an excellent movie, wasn't it?)
So here's an update from the Route 7 project's Chief Inspector, Mark Vinisko. "The wings have been poured and the parapet wall will be poured tomorrow," he said a few moments ago. "Traffic will be switched on Friday, the remaining overlay will be done the first week of July and there'll be four lanes by mid-July."
None too soon.